Tuesday, September 15, 2009

Final Paving Schedule

The final layer of asphalt is scheduled to be placed on Thursday, September 17th. Early Thursday morning, the existing asphalt surface will be coated with fresh oil and sand. The oil will help the top coat of asphalt to bond to the existing layer. The layer of sand is to help to prevent tracking the oil onto driveways. We ask residents to please try to keep driving to a minimum between 7:00am and 9:00am while the oil dries. If the oil must be driven on, drivers should proceed slowly to help prevent splattering onto the vehicle.

The contractor will follow up immediately with the placing of 2 inches of asphalt on Thursday and Friday. Of course paving is weather contingent, if paving cannot start Thursday, then it will begin the next available dry day.

Access to driveways will still be available, although there may be short delays during the paving process. Please adjust schedules accordingly. We will be in contact with the school buses to notify them of the schedule.