Tuesday, June 9, 2009

Current Activity

The stone has been placed for asphalt paving on Balmoral and Kenilworth. The first layer of asphalt will be completed this week.

Water main is now installed on Ridgewood East. It has been pressure tested and service installation on that road will begin this week. Services have been completed along the south end of Ridgewood West and Pleasant. All that remains for water main installation is along the north end of Ridgewood West, Glen Oak Drive and Linden Lane.

The contractor will continue to work on water main, with the plan to have all water main and service lines installed by mid next week. Once that is complete, work will continue on the storm sewer, which has been installed up to Pleasant and Ridgewood East.