Thursday, May 28, 2009

Update

Lots of work has been going on around Glen Oak Acres! The storm sewer is now complete on Balmoral and Kenilworth and the contractor began removing pavement today. The plan is to place the binder level (bottom level) of asphalt on those two streets to be able to move away from them while work continues throughout the acres. The asphalt work should happen within the next couple of weeks.

Underground work has continued along Pleasant and Ridgewood East. Mostly water main is being installed right now. Water main along Pleasant is complete and the crew is now going to work their way north on Ridgewood East.