Monday, August 31, 2009

Now that the binder level of asphalt is complete, there are several things that need to be done before surface can be placed. Some things have all ready begun; as many drivers may have noticed, the frames of the structures have been broken out, meaning the binder asphalt was opened up so that the frame of the structure can be placed at the correct elevation. The parkway restoration has begun, starting with the clearing and smoothing out of the areas that will get restored, and then placing topsoil. The sod will not be placed until AFTER the surface asphalt has been installed.