Thursday, August 6, 2009

On Friday, August 7, DiMeo will begin grading the remaining roads, West Ridgewood (north of Pleasant Lane), Linden Lane and Glen Oak Drive, in preparation for paving. The schedule is to place the binder lift (bottom layer) of asphalt on those roads late next week. We ask residents to please plan accordingly when coming and going on any day paving is taking place; they may need to wait a few minutes or find a different route.

After the contractor has completed paving the first layer of asphalt on all streets, work will begin to remove all of the debris from the site, grade the parkways and place topsoil, in preparation for sod. The sod work will not begin until September, when temperatures are cool enough to ensure that the sod does not die in the heat of the day.